Timeline

05/29/2015 - Signed purchase agreement and paid initial payment
06/05/2015 - Mortgage application signed
06/12/2015 - Guardian appointment - Rescheduled 
06/12/2015 - T.A.C Tile tile and flooring finishes selections
07/02/2015 - Guardian home security and electrical selections
07/25/2015 - Finalization selections
09/11/2015 - Pre-construction meeting
09/14/2015 - Broke ground 
09/18/2015 - Footing poured 
10/10/2015 - Completed first floor framing
10/16/2015 - Completed 2nd and third floor framing
10/26/2015 - Started roof trusses installation
10/30/2015 - Roof installation completed
11/13/2015 - Shingles installation completed, house wrapping and windows installation started
11/19/2015 - HVAC installation started
11/23/2015 - Plumbing installation started 
11/30/2015 - Electrical/Guardian wiring installation
12/04/2015 - Pre-drywall inspection
02/11/2016 - New Homeowner's Orientation and final inspection
02/17/2016 - Close date (Re-scheduled)
02/29/2016 - Close date
03/05/2016 - Moved in 
03/16/2016 - Pre-30 day walkthrough 